Mezzanine Floor And Heavy Duty Cantilever Racking Project in Costa Rica

Oct 19, 2026 Leave a message

Project Overview

 

This Costa Rica project combines a structural steel mezzanine floor platform with a heavy duty cantilever racking system. The mezzanine uses an I-beam structure with reinforced columns and beams, while the cantilever racks provide dedicated storage space on the first level of the mezzanine.

 

Designed around two integrated storage structures, the project combines an elevated steel platform with heavy-duty cantilever storage for a warehouse application.

 

Mezzanine Floor and Heavy Duty Cantilever Racking Project in Costa Rica

 

Project Specifications

Item Project Details
Project Location Costa Rica
Storage Solution Mezzanine Floor Platform + Heavy Duty Cantilever Racking
Mezzanine Structure I-beam steel structure
Structural Components Reinforced columns and beams
Floor Decking Anti-slip steel decking
Mezzanine Load Capacity 800 kg/m²
Cantilever Rack Load Capacity 2,000 kg per layer
Project Documentation Assembly process photos, on-site engineering guidance photos and vertical video

 

1. Structural Steel Mezzanine Floor Platform

 

The mezzanine floor platform uses an I-beam structural design with reinforced steel columns and beams. Anti-slip steel decking forms the floor surface, providing a durable platform for the intended warehouse storage application.

 

With a specified load capacity of 800 kg/m², the platform is designed around the project's floor loading requirements. Its structural configuration brings together the main steel framework, supporting members and floor decking as an integrated system.

 

Key specifications:

  • I-beam structural framework
  • Reinforced steel columns and beams
  • Anti-slip steel floor decking
  • Rated platform load capacity of 800 kg/m²

 

4

19

29

2. Heavy Duty Cantilever Racking System

 

A heavy duty cantilever racking system is positioned on the first level of the mezzanine. The rack system provides a dedicated storage structure within the elevated platform layout.

 

Each cantilever rack layer has a specified load capacity of 2,000 kg. This capacity is a rack-level specification and is distinct from the mezzanine's distributed floor load rating.

 

The rack arrangement and mezzanine structure must be assessed together according to the actual layout, rack loading and structural design requirements.

 

Key specifications:

  • Heavy duty cantilever racking
  • Installed on the first level of the mezzanine
  • Rated load capacity of 2,000 kg per layer
  • Integrated with the project's elevated storage arrangement

 

3. On-Site Assembly and Engineering Guidance

 

This project includes documentation of the assembly process, along with photos of engineers providing on-site installation guidance and a vertical video showing the project work.

 

These materials document the practical execution of the storage system, from structural assembly to on-site technical guidance. They also provide project-specific evidence for customers evaluating mezzanine platforms and heavy duty cantilever racking for similar warehouse applications.

 

The installation sequence, structural connections and final configuration should be reviewed against the project's approved drawings and engineering requirements.

 

An Integrated Mezzanine and Cantilever Racking Solution

 

The Costa Rica project demonstrates how a structural mezzanine floor and heavy duty cantilever racking can be combined within one warehouse storage project. The mezzanine provides the elevated platform, while the cantilever rack system delivers dedicated storage capacity at the designated level.

 

For warehouse projects involving heavy floor loads and cantilever storage, HEDA SHELVES can provide project-specific storage equipment solutions based on the intended application, layout and loading requirements.

 

Planning a warehouse mezzanine or cantilever racking project? Contact HEDA SHELVES to discuss your warehouse layout, storage requirements and project specifications.